Seawater Reverse Osmosis

Chabahar 2

23,750 m³ / in 24h

Sistan and BaluchestanSWRO23,750 m³ / in 24h
Discuss a similar project
chabahar (40)
01/13

chabahar (40)

Technical details

Overview

After the successful construction and operation of Phase I, contracts for the second and third phases were won in separate tenders. Feed water is supplied from the Oman Sea via a direct intake system, pretreated through gravity sand filters, then directed to cartridge filters and SWRO units. Permeate enters the Chabahar and Konarak water distribution network.

Main components

Direct intake system and piping, gravity sand filters, filtered water pump station and reservoir tank, chemical dosing unit, cartridge filters, high pressure pumps, pressure vessels and membranes, storage tanks, CIP unit, permeate pumping station and pipeline.

Associated companies

Design and equipment by Axiom (Austria) and B2A (Austria). All other work carried out by NVCo.

Phase II

Contract awarded
2013
Contract type
B.O.O.
Duration to start-up
10 months
Contract period
10 years from start-up
Contractual capacity
15,000 m³ / in 24h
Final nominal capacity
23,750 m³ / in 24h